Three MW Power Boost on LM 6000 in Mexico with MeeFog

Procter & Gamble in Mexico installed a MeeFog evaporative cooling system in their LM 6000 gas turbine in 2006. In 2013 they expanded their system by adding another pump and additional nozzles. The Meefog skid has two pumps and provides five stages of fogging, producing a 3 MW power boost.

Project Conditions:

Location: Apizaco Tlaxcala, Mexico
Hot day conditions: 23.3° C with 14.5° C wet bulb
Elevation: 2,444 meters above sea level
Mee’s scope of work: Supervision during installation and commissioning
Max power boost per GT: 3 MW

Fog System Design:

Fogging stages: 5
Operating pressure: 2,000 psi
Fog droplet size: 12 microns
Nozzle flow rate: 0.17 lpm per nozzle
MeeFog nozzle count: 260
Pump skid power: 20 HP

Learn More

Want to learn more about successful Meefog systems installation projects and case studies?

Other Related Blog Articles

MeeFog Adds 64MW of Power Augmentation to Mexican Power Plant

Case Study: Tuxpan III & IV Combined Cycle Power Plant needed to maximize its power output to......

Power Output Boost of 28 MW Using Wet Compression

Project Profile: MeeFog wet compression systems fitted onto two Siemens SGT-5000FD2 gas turbines in the state of......

32 MW Power Boost On a Siemens Westinghouse W501FC

Project Profile: A power station in Mexico installed two MeeFog systems on a Siemens Westinghouse W501FC gas......